Scorecards for completed and in progress Harvard LEED for New Construction projects are listed below, followed by LEED submittals for completed projects. To print the scorecards, download the summary, or detailed (for completed projects only), as Excel worksheets, formatted for legal paper.
LEED-NC PROJECT SCORECARDS
COMPLETED
IN PROGRESS*
| Building | LEED Rating Attempting |
Version |
Expected Completion |
Total |
SS |
WE |
EA |
MR |
EQ |
ID |
| First Science Center, ADG | Gold |
v2.2 | on hold | 48 | 14 | 4 | 8 | 5 | 12 | 5 |
| Book Depository - Module 7, HUL | Gold | v2.2 | July 2009 | 40 | 8 | 4 | 8 | 6 | 9 | 5 |
| Byerly Hall, RAD | Gold |
v2.2 | Oct 2008 | 36 | 8 | 2 | 3 | 3 | 15 | 5 |
| 32 Quincy St. (Fogg Art Museum), ADG/HUAM | Gold | v2.2 | In Design | 41 | 9 | 5 | 6 | 6 | 10 | 5 |
| 641 Huntington Ave, HMS | Gold |
v2.2 | July 2009 | 45 | 8 | 4 | 11 | 6 | 11 | 5 |
| Northwest Corner, HLS | Gold |
v2.2 | Dec 2011 | 42 | 11 | 3 | 6 | 5 | 13 | 4 |
| Weld Hill, Arnold Arboretum | Gold |
v2.1 | Nov 2009 | 46 | 10 | 4 | 7 | 6 | 14 | 5 |
| 22 Plympton St, HSPH | Certified | v2.2 | June 2008 | 31 | 6 | 2 | 6 | 2 | 10 | 5 |
| Total Points: Certified: 26-32, Silver: 33-38, Gold: 39-51, Platinum: 52-69 | ||||||||||
* Scorecards for projects in progress are updated frequently, and subject to change until accepted by the USGBC.
SUBMITTALS FOR COMPLETED LEED-NC PROJECTS
SUSTAINABLE SITES
Construction Activity Pollution Prevention (Prerequisite 1)
LEED v2.2
LEED v2.1
- Five Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall*
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
- 60 Oxford St.
- One Western Avenue
Site Selection (SSc1)
All of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone
- Hamilton Hall
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
Development Density and Community Connectivity (SSc2)
12 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.*
- Blackstone*
- Hamilton Hall
- Schlesinger Library
- Wyss Hall
- Zero Arrow Street
LEED v2.0
Brownfield Redevelopment (SSc3)
5 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
- 60 Oxford Street
Alternative Transportation: Public Transportation Access (SSc4.1)
12 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall*
- Schlesinger Library
- Wyss Hall
- Zero Arrow Street
LEED v2.0
Alternative Transportation: Bicycle Storage and Changing Rooms (SSc4.2)
All of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
- 60 Oxford St.
- One Western Ave.
Alternative Transportation: Low Emitting and Fuel Efficient Vehicles (SSc4.3)
12 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Alternative Transportation: Parking Capacity and Carsharing (SSc4.4)
11 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEEE v2.0
Site Development: Protect or Restore Habitat (SSc5.1)
1 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.1
Site Development: Maximize Open Space (SSc5.2)
9 out of 13 of Harvard's LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Stormwater Design: Quantity Control (SSc6.1)
9 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
- 60 Oxford St.
- One Western Ave.
Stormwater Design: Quality Control (SSc6.2)
6 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Heat Island Effect: Non-roof (SSc7.1)
12 out of 13 Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone
- Hamilton Hall*
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
Heat Island Effect: Roof (SSc7.2)
8 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Light Pollution Reduction (SSc8)
6 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
WATER EFFICIENCY
Water Efficient Landscaping: Reduce by 50% (WEc1.1)
8 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Water Efficient Landscaping: No Potable Water Use or No Irrigation (WEc1.2)
3 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.1
Innovative Wastewater Technologies (WEc2)
This credit has not yet been achieved by a project at Harvard.
Water Use Reduction (20% WEc3.1, 30% WEc3.2)
10 out of 13 of Harvard's completed LEED-NC projects have achieved these credits.
LEED v2.2
LEED v2.1
ENERGY AND ATMOSPHERE
Fundamental Commissioning of the Building Energy Systems (EA Prerequisite 1)
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone
- Hamilton Hall*
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
Minimum Energy Performance (EA Prerequisite 2)
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
- 60 Oxford St.
- One Western Ave.
Fundamental Refrigerant Management (EA Prerequisite 3)
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall*
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
Optimize Energy Performance (EAc1.1-1.10)
11 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St. (4) (28.2%)
- 90 Mount Auburn St. (4) (32.2%)
- Blackstone (8) (45.2%)*
- Hamilton Hall (4) (22.1%)*
- Schlesinger Library (5) (25.8%)
- Wyss Hall (3) (18.3%)
- Zero Arrow St. (2) (35.6%)
LEED v2.0
On-Site Renewable Energy (5% EAc2.1, 10% EAc2.2, 20% EAc2.3)
1 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
Enhanced Commissioning (EAc3)
11 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Schlesinger Library
- Zero Arrow St.
LEED v2.0
- 60 Oxford St.
- One Western Ave.
Enhanced Refrigerant Management (EAc4)
7 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Measurement & Verification (EAc5)
6 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Green Power (EAc6)
11 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
MATERIALS & RESOURCES
Storage & Collection of Recyclables (Prerequisite 1)
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
- 60 Oxford St.
- One Western Ave.
Building Reuse: Maintain 75% (MRc1.1) of Existing Walls, Floors, and Roof (95% MRc1.2)
7 out of 13 of Harvard's completed LEED-NC projects have achieved these credits.
LEED v2.2
LEED v2.1
Building Reuse: Maintain 50% of Interior Non-structural elements (MRc1.3)
This credit has not yet been achieved by a project at Harvard.
Construction Waste Management: Divert 50% (MRc2.1) from Disposal (75% MRc2.2)
12out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
- 10 Akron St. (2) (91%)
- Aldrich Hall (2)
- Gallatin Hall (2) (98.4%)
- Rockefeller Hall (2) (84.95%)
LEED v2.1
- 5 Cowperthwaite St. (2) (96.7%)
- 90 Mount Auburn St.* (2) (96.3%)
- Blackstone* (2) (99.4%)
- Hamilton Hall* (2) (97.1%)
- Schlesinger Library (2) (91.3%)
- Wyss Hall (2) (96.3%)
- Zero Arrow St. (2) (81.5%)
LEED v2.0
- One Western Ave. (2) (78%)
Materials Reuse: (5% MRc3.1 and 10% MRc3.2)
These credits have not yet been achieved by a project at Harvard.
Recycled Content: Post-consumer + 1/2 Pre-Consumer) (10 % MRc4.1, 20% MRc4.2)
11 out of 13 of Harvard's completed LEED-NC projects have achieved these credits.
LEED v2.2
- 10 Akron St. (2) (21%)
- Gallatin Hall
- Rockefeller Hall (1) (18.67%)
LEED v2.1
- 5 Cowperthwaite St. (2) (31.6%)
- 90 Mount Auburn St.
- Blackstone* (2) (10.5%)
- Hamilton Hall* (2) (10.4%)
- Schlesinger Library (5.7%)
- Wyss Hall
- Zero Arrow St. (2) (13.4%)
LEED v2.0
Regional Materials: 10% (MRc5.1) Extracted, Processed and Manufactured Regionally (20% MRc5.2)
11 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
- 10 Akron St. (2) (21.6%)
- Rockefeller Hall (2) (42.45%)
LEED v2.1
- 5 Cowperthwaite St. (2) (76.9%, 67.2%)
- 90 Mount Auburn St. (2) (50.3%, 13.5%)
- Blackstone* (2) (33.5%, 11.5%)
- Hamilton Hall* (2) (72%, 12.4%)
- Schlesinger Library (27.6%, 0%)
- Wyss Hall (2) (66.3%, 18.2%)
- Zero Arrow St. (2) (62.7%, 56.3%)
LEED v2.0
- 60 Oxford St. (23.81%, 1.05%)
- One Western Ave.
Rapidly Renewable Materials (MRc6)
1 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.1
Certified Wood (MRc7)
5 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.1
LEED v2.0
- 60 Oxford St.
- One Western Ave. (51.56%)
INDOOR ENVIRONMENTAL QUALITY
Minimum IAQ Performance (Prerequisite 1)
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall
- Schlesinger Library
- Wyss Hall*
- Zero Arrow St.
LEED v2.0
- 60 Oxford St.
- One Western Ave.
Environmental Tobacco Smoke Control (Prerequisite 2)
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall
- Schlesinger Library
- Wyss Hall*
- Zero Arrow St.
LEED v2.0
Outdoor Air Delivery Monitoring (EQc1)
5 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- Blackstone*
- Schlesinger Library
- Wyss Hall
Increased Ventilation (EQc2)
7 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Construction IAQ Management Plan: During Construction (EQc3.1)
9 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Construction IAQ Management Plan: Before Occupancy (EQc3.2)
10 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Low Emitting Materials: Adhesives & Sealants (EQc4.1)
11 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
- 60 Oxford St.
- One Western Ave.
Low Emitting Materials: Paints & Coatings (EQc4.2)
11 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Low Emitting Materials: Carpet Systems (EQc4.3)
12 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
Low Emitting Materials: Composite Wood and Agrifiber Products (EQc4.4)
4 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Indoor Chemical & Pollutant Source Control (EQc5)
10 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Controllability of Systems: Lighting (EQc6.1)
9 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Controllability of Systems: Thermal Comfort (EQc6.2)
6 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Thermal Comfort: Design (EQc7.1)
8 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Thermal Comfort: Verification (EQc7.2)
5 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
Daylight & Views: Daylight 75% of Spaces (EQc8.1)
9 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Daylight & Views: Views for 90% of Spaces (EQc8.2)
11 out of 13 of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall*
- Schlesinger Library
- Wyss Hall*
- Zero Arrow St.
LEED v2.0
- One Western Avenue
INNOVATION AND DESIGN PROCESS
Educational Program
6 out of 13 of Harvard's completed LEED projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Green Cleaning
7 out of 13 of Harvard's completed LEED projects have achieved this credit.
LEED v2.2
- 10 Akron St.
- Aldrich Hall (file size: 9.5 MB)
LEED v2.1
LEED v2.0
Commuter Choice
5 out of 13 of Harvard's completed LEED projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Green Power, 100% Renewable Energy
6 out of 13 of Harvard's completed LEED projects have achieved this credit.
LEED v2.2
LEED v2.1
LEED v2.0
Construction Waste Management, Exemplary Performance
7 out of 13 of Harvard's completed LEED projects have achieved this credit.
LEED v2.2
LEED v2.1
Local Materials, Exemplary Performance
3 out of 13 of Harvard's completed LEED projects have achieved this credit.
LEED v2.2
LEED v2.1
Heat Island Effect, Non Roof, Exemplary Performance
Maximizing Open Space, Exemplary Performance
Water Use Reduction, Exemplary Performance
2 out of 13 of Harvard's completed LEED projects have achieved this credit.
LEED v2.2
LEED v2.1
Recycling, Exemplary Performance
5 out of 13 of Harvard's completed LEED projects have achieved this credit.
LEED v2.2
LEED v2.1
Low Mercury Lighting
This credit has not yet been achieved by a project at Harvard.
LEED Accredited Professional (ID credit 2.0)
All of Harvard's completed LEED-NC projects have achieved this credit.
LEED v2.2
LEED v2.1
- 5 Cowperthwaite St.
- 90 Mount Auburn St.
- Blackstone*
- Hamilton Hall
- Schlesinger Library
- Wyss Hall
- Zero Arrow St.
LEED v2.0
- 60 Oxford St.
- One Western Ave.
Updated: Monday, November 23, 2009 10:24 AM